Bicol Airport Takes Shape

 4 March 2021


Your Website Title

Bicol International Airport takes shape.

Posted by Department of Transportation - Philippines on Wednesday, March 3, 2021
 

The Transport Department has announced that construction of the P4.978-billion Bicol International Airport is now 75% complete, the Department of Transportation (DOTr) said Wednesday.

It is slated for completion and to open on the fourth quarter of this year. The actual construction of the airport started in December 2016. 

The 75% completion rate is the project’s overall progress rate, comprising Packages 2A and 2B.

Package 2A of the airport project is at 89.784%. 

Package 2A covers the airport’s landside facilities, such as the Administration Building, Air Traffic Control Building, Crash Fire Rescue Building, and the Maintenance Building.

Meanwhile Package 2B of the airport project is now 52.699% complete. 

It covers the construction of the passenger terminal building (PTB), taxiway, runway extension, and other site development works.