DOTC Rolls 48 Million To Start Project
April 10, 2013
Airport upgrades includes expansion and improvement of the passenger terminal building (PTB) and the extension of the runway to conform to type 3C airport standards.
The runway extension, on the other hand, will lengthen the runway from 1,890 m. to 2,010 m. The additional 120 meters is designed to insure operational safety of critical aircraft operating at the airport which is servicing regular A320 planes.
April 10, 2013
President Benigno S. Aquino III led the ceremonial
groundbreaking for the upgrading of Roxas City Airport Wednesday to put the airport to international standards.
Airport upgrades includes expansion and improvement of the passenger terminal building (PTB) and the extension of the runway to conform to type 3C airport standards.
The two projects are part of a P215-million Roxas Airport Development project. The project components are:
- Runway Extension and Passenger Terminal Building Expansion ₱ 91,150,000.00
- Site Acquisition ₱ 18,000,000.00
- Runway asphalt overlay ₱ 24,240.000.00
- Runway Lightning System ₱ 91,150,000.00
- Crash, Fire, Rescue Tender ₱ 33,500,000.00
Currently two projects, with a combined approved budget for contract (ABC) of
P48.1-million, were advertised for bidding on October 19, 2012 and were
awarded to contractor MAC Builders on December 28, 2012. Other projects for the airport are all in various stages of procurement.
The PTB expansion project will increase the existing 875-sqm terminal’s size by 626 sqm, bringing up the total floor area to 1,511 sqm and bumping up its design capacity from 153,000 passengers per year to 291,000 passengers per year.
Roxas Airport registered a traffic of 217,552 passengers in 2012.
The PTB expansion project will increase the existing 875-sqm terminal’s size by 626 sqm, bringing up the total floor area to 1,511 sqm and bumping up its design capacity from 153,000 passengers per year to 291,000 passengers per year.
Roxas Airport registered a traffic of 217,552 passengers in 2012.
The runway extension, on the other hand, will lengthen the runway from 1,890 m. to 2,010 m. The additional 120 meters is designed to insure operational safety of critical aircraft operating at the airport which is servicing regular A320 planes.